Allenbuild Ltd

Brief:

We were instructed to complete a phase 2 intrusive investigation and develop a sampling strategy and in due course undertake verification.

Project:

The site had previously been an army barracks in Hampshire and is to be redeveloped in to residential homes with private gardens. The development is part of a complex, £1bn, multi-partner, 15-year collaborative and transformational place-making programme  to transform the area from ‘garrison town to green town’ by 2030.

An intrusive investigation had already been completed, GO Contaminated Land Solutions developed a sampling strategy and conducted further investigation to determine the extent of contamination and inform a remediation strategy.